Tile Flooring
April 11, 2023
-
Lighting Grid
April 8, 2023
-
Balcony Trim & Railings
March 18, 2023
-
Stairs
January 12, 2023
-
Painting
September 22, 2022
-
Drywall Delivery
October 22, 2021
-
Rafter Sheathing Complete
June 6, 2021
-
Center Wall Complete
July 8, 2020
-
Rafters Mostly Done
June 13, 2020
-
Plumb Side Walls
June 12, 2020
-
Ledger Board
June 6, 2020
-
Final Walls & Ridge Beam Up
June 5, 2020
-
Fourth Wall Up
May 30, 2020
-
Three Walls Raised
May 23, 2020
-
First Wall
May 16, 2020
-
Lumber Delivery