Siding Started
July 29, 2017
-
Repairs & Flashing
July 28, 2017
-
Trim Z-Angle
July 26, 2017
-
Rake Trim & Base Angle
July 23, 2017
-
Doors
July 22, 2017
-
Perimeter Excavated
July 21, 2017
-
Knock-in Bridging
July 20, 2017
-
Cross Bracing
July 15, 2017
-
Steel Frame Complete
July 9, 2017
-
Scissor Lifts
July 7, 2017
-
Garden Plot
July 2, 2017
-
Basement Framing
June 20, 2017
-
Corner Column Fixed
June 1, 2017
-
Second section up
May 28, 2017
-
The Barn Raising
May 27, 2017
-
Building Kit Delivery
May 26, 2017
-
Insulation Delivery
May 25, 2017
-
Forklift Rental
May 24, 2017
-
First Snow
November 21, 2016
-
Pouring Concrete
November 12, 2016
-
Breaking Ground
November 4, 2016
-
Clearing Trees
November 1, 2016
-
Early Design Work
October 29, 2016
-
Getting Started
August 28, 2016