Lumber Delivery
March 9, 2020
-
Framing & Mechanical Design
February 6, 2020
-
Power & Retaining Walls
August 19, 2019
-
Trenching
June 12, 2019
-
Design Changes
-
Blueprints
May 2, 2018
-
Work Lighting Complete
April 8, 2018
-
Design Work Continued
April 3, 2018
-
Architectural Model
December 21, 2017
-
Work Lighting Started
December 17, 2017
-
Ready for Winter
December 16, 2017
-
First Snow
December 10, 2017
-
Chicken Dome
December 8, 2017
-
Final Grading Complete
December 6, 2017
-
Clean Up
December 2, 2017
-
Roof Completion
December 1, 2017
-
Wind Storm
October 30, 2017
-
Falling Down
October 26, 2017
-
Play Set
October 21, 2017
-
Second End Wall Siding Complete
October 19, 2017
-
Around the Door
October 18, 2017
-
Roofing Started
October 11, 2017
-
Second End Wall Siding Started
September 25, 2017
-
First End Wall Siding Complete
September 23, 2017
-
First End Wall Siding Continued
September 21, 2017
-
First End Wall Siding Started
September 18, 2017
-
Second Side Wall Siding Complete
-
Second Side Wall Siding Started
September 3, 2017
-
Scaffolding
August 21, 2017
-
End Wall Column Repair
August 3, 2017
-
Older Posts